CCT Representation Project Work Session - June 15, 2004 (RX)
Date / Time: 2004.06.15 13:15~16:30
Venue: Oracle (Redwoord Shores, CA) (RY)
Agenda & Proceedings (S7)
- (S9)
- intro of the sub-team participants (SA)
- scope this phase of the project -- getting a first completed version of the draft CCTONT out (SB)
- build rapport among the sub-team members so that work can continue virtually (SC)
- setup a short term plan and a work schedule (SD)
- (SH)
- 2. Quick walkthru of where the project now stands. Navigation through resources already linked to through the CctRepresentation project page and the ontolog-wiki demonstrated. (SI)
- (SL)
- 4. Scope of this phase of the project was discussed. (SM)
- In particular, we are planning to come up a CCTONT that would allow us to present two versions of the CCT-Ontology, (SN)
- (i) one that only includes the 10 approved core component types (we might recommend reducing it to 9), ref: the "types" under the column "CCT Dictionary Entry Name" on Table 8-1, pages 95-97, of CCTS v2.01 (see: http://ontolog.cim3.net/file/work/CCT-Representation/CEFACT-CCTS-Version-2pt0extract.pdf), and (SO)
- (ii) the other would, besides the above, include the Approved Core Component Type Content and Supplementary Components (as listed under the Name" column on Table 8-2, or the "CCT Compoents" column of the abovementioned table 8-1 in the same document). Total: 10 (or 9) plus 44 terms. (SP)
- (SQ)
- 5. Short-term workplan discussed and adopted: (SR)
- 5.1 Peter to parse Adam's earlier mapping against the CCTS specification and make any necessary adjustments. Target completion: Wed 2004.06.16 (SS)
- 5.2 Adam to develop the draft CCTONT as scoped in above 4. Let's call this v0.2. Target completion: Thu 2004.06.17 (ST)
- 5.3 Garret, Nenad and Peter (hopefully, Tim & Sue also) to review and make clarifications, comments and sugestions. Target completion: Sat 2004.06.19 (SU)
- 5.4 Incorporated necessary changes from 5.3, update and publish draft CCTONT v0.4. Target completion: Mon 2004.06.21 (SV)
- 5.5 Peter to start a wiki page to collect feedback and lessons learned, from the team members and the community, that are relevant for submission to the eBusiness Standards developers. (SW)
- 5.6 Pass draft CCTONT v0.4 on to PatCassidy for import via the ProtegeKIF work product. (SX)
- 5.7 Invite review, clarifications, comments and sugestions from the ontolog community. Open for 1 week: 2004.06.21~28. (SY)
- 5.8 Incorporated necessary changes from 5.7, update and publish draft CCTONT v0.6. Target completion: Wed 2004.06.30 (SZ)
[Note: it was noted that Nenad will be traveling for about 2 weeks, starting 2004.06.24.
Garret will be out of the country week of 2004.06.21. All the more reason that we need
to get the above completed this week, to allow us to pass this work onto PatCassidy for
the next work segment, and to get ready for the OntologWorkshop_July_2004.] (T0)
- (T1)
- 6. Adam familiarize the team members on the platform we are working on by giving a brief intro to SUO-KIF, SUMO and SIGMA-kee. (T2)
- (T6)
- All: please review above. Corrections, comments & suggestions welcomed. (T7)
- ... add content here ... (T8)